(Cont.) Convention On The Prohibition Of The Development, Production,
Stockpiling And Use Of Chemical Weapons And On Their Destruction
"United Nations, 1993, pp. 1 - 172"

         (c) Process flow diagram of the facility before, and as appropriate, after the conversion;

         (d) Detailed inventory of equipment, buildings and structures and other items to be destroyed and of the buildings and structures to be modified;

         (e) Measures to be applied to each item on the inventory, if any;

         (f) Proposed measures for verification;

         (g) Security/safety measures to be observed during the conversion of the facility; and

         (h) Working and living conditions to be provided for inspectors.

Review of detailed plans

79.  On the basis of the detailed plan for conversion and proposed measures for verification submitted by the State Party, and on experience from previous inspections, the Technical Secretariat shall prepare a plan for verifying the conversion of the facility, consulting closely with the State Party. Any differences between the Technical Secretariat and the State Party concerning appropriate measures shall be resolved through consultations. Any unresolved matters shall be forwarded to the Executive Council for appropriate action with a view to facilitate the full implementation of this Convention.

80.  To ensure that the provision of Article V and this Part are fulfilled, the combined plans for conversion and verification shall be agreed upon between the Executive Council and the State Party. This agreement shall be completed not less than 60 days before conversion is planned to begin.

81.  Each member of the Executive Council may consult with the Technical Secretariat on any issue regarding the adequacy of the combined plan for conversion and verification. If there are no objections by any member of the Executive Council, the plan shall be put into action.

82.  If there are any difficulties, the Executive Council should enter into consultations with the State Party to reconcile them. If any difficulties remain unresolved, they should be referred to the Conference. The resolution of any differences over methods of conversion should not delay the execution of other parts of the conversion plan that are acceptable.

83.  If agreement is not reached with the Executive Council on aspects of verification, or if the approved verification plan cannot be put into action, verification of conversion shall proceed through continuous monitoring with on-site instruments and physical presence of inspectors.